MBDBE final supporting statement PART 50 final amended

MBDBE final supporting statement PART 50 final amended.docx

10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities

OMB: 3150-0011

Document [docx]
Download: docx | pdf

SUPPORTING STATEMENT FOR


INFORMATION COLLECTIONS CONTAINED IN


MITIGATION OF BEYOND-DESIGN-BASIS EVENTS

FINAL RULE


10 CFR PART 50


(OMB CLEARANCE NO. 3150-0011)


DESCRIPTION OF THE INFORMATION COLLECTION


The U.S. Nuclear Regulatory Commission (NRC) is amending its regulations to establish regulatory requirements to mitigate beyond-design-basis events. The Mitigation of Beyond‑Design-Basis Events (MBDBE) final rule achieves the following regulatory objectives:


  1. Make the requirements of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,1 and Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,2 generically applicable.


  1. Establish regulatory requirements for documentation of changes.


  1. Address a number of petitions for rulemaking (PRMs) submitted following the March 2011 Fukushima Dai-ichi event.


This analysis addresses the information collections associated with the MBDBE rule requirements that contain an incremental change in burden relative to existing rules, Orders, and industry initiatives. The MBDBE rule encompasses provisions that are currently being implemented by Order EA-12-049 and Order EA-12-051. The paperwork burden associated with the MBDBE rule largely results from the one-time licensee’s review of the rule to confirm compliance with the Order requirements (i.e., a comparison of the MBDBE rule requirements with the Orders and updates to procedures, programs, or plans).


Affected Entities


The MBDBE rule requirements impact nuclear power plants (NPPs) at the site level. Therefore, the incremental burdens associated with the MBDBE rule are expressed in terms of NPP sites. The NRC estimates the burdens incurred by 55 operating sites, based on the announced decommissioning intentions (i.e., Fort Calhoun and Oyster Creek have entered decommissioning; Clinton, FitzPatrick, Pilgrim, and Quad Cities have announced plans to decommission). One of the operating sites (i.e., Vogtle) is constructing new AP1000 reactor units. Because information collections are estimated by site, the new reactors are accounted for as part of the operating site on which they are co-located.


A. JUSTIFICATION


1. Need for and Practical Utility of the Information


The NRC has developed the MBDBE rulemaking, in large measure, to make generically applicable the regulatory actions taken following the events at the Fukushima Dai-ichi nuclear power plant resulting from the March 11, 2011, Great Tōhoku Earthquake and subsequent tsunami. Current NRC regulations do not incorporate requirements to implement strategies and guidelines for the mitigation of beyond-design-basis external events (referred to, in the nuclear industry, as the diverse and flexible coping strategies (FLEX)). These strategies are implemented by FLEX support guidelines or FSGs, and provide additional capability to address the uncertainties associated with beyond-design-basis external events (e.g., events arising from severe natural phenomena). The MBDBE rulemaking makes generically applicable requirements similar to those imposed by Order EA-12-049 and Order EA 12-051.


Operating power reactor licensees and a number of combined license holders currently are subject to these Order requirements and license conditions. Any future licensees would not be covered by the Order requirements. In the absence of a rule, these requirements would need to be implemented for new reactor sites through additional Orders or license conditions (as was done for all combined licenses issued to date), which would impose additional costs on the NRC.


The MBDBE rulemaking, both the regulation and its supporting guidance, also enhances regulatory efficiency by reflecting stakeholder feedback provided in response to the proposed rule (80 FR 70609, November 13, 2015), and lessons learned from the implementation of the Orders, including any challenges or unintended consequences associated with implementation.


The specific information collections associated with the MBDBE revisions and amendments to Parts 50 and 52 are identified below.


Section 50.34(i) requires applicants for power reactor operating licenses to include plans for implementing the requirements in 10 CFR 50.155, “Mitigation of Beyond-Design-Basis Events,” including a schedule for achieving full compliance, a description of the integrated response capability, and the equipment and location of the equipment upon which the strategies rely. These requirements were established under Order EA‑12-049 and licensees have already completed this requirement.


Section 50.155 requires licensees to review their previous compliance under Orders EA-12-049 and EA-12-051 against the MBDBE rule requirements to confirm their compliance with the MBDBE rule, as well as to make changes to procedures, programs, and plans to reference the new MBDBE rule requirements (rather than the Order requirements). Sites will incur a one‑time recordkeeping burden to review procedures, programs, and plans to confirm that they are consistent with the rule requirements. The incremental one-time recordkeeping burden associated with this requirement is included in Table 2.


Section 50.155(b)(1) requires licensees to develop strategies and guidelines to mitigate beyond-design-basis external events from natural phenomena that are developed assuming a loss of all ac power concurrent with either a loss of normal access to the ultimate heat sink or loss of normal access to the normal heat sink. These requirements were established under Order EA‑12-049 and licensees have already completed this requirement.


Section 50.155(b)(2) requires licensees to develop strategies and guidelines to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities under the circumstances associated with loss of large areas of the plant impacted by the event, due to explosions or fire. These requirements were established under Order EA‑02-026 and licensees already comply with this requirement.


Section 50.155(f) requires licensees to maintain documentation of changes in the implementation of the requirements of section 50.155. These requirements were established under Order EA‑12-049.


Section 52.80(d) requires applicants for power reactor combined licenses under Part 52 to include in their applications information on the plan for implementing the requirements of 10 CFR 50.155(b), including a schedule for achieving compliance as well as a description of the integrated response capability required by 10 CFR 50.155(b) and the requirement and planned locations of the equipment on which the strategies and guidelines will rely. This is the same requirement as that contained in Section 50.34(i) for applicants for a new power reactor operating license under Part 50. The NRC does not expect any new applicants under Part 50 for a power reactor operating license or under Part 52 for a combined license for the next three years. A supporting statement has been submitted under 10 CFR Part 52 (3150-0151) to cover the requirement for applicants for combined licenses to include plans for compliance with 50.155.


Additional voluntary guidance for implementing the information collections associated with the MBDBE revisions and amendments to Parts 50 and 52 can be found at https://www.nrc.gov/reading-rm/doc-collections/reg-guides/power-reactors/rg/.


2. Agency Use of the Information


The information identified will be used to determine licensee compliance with the requirements of the MBDBE rule and thus ensure that the power reactor licensees have developed additional capability to respond to events exceeding the external events design basis of the facility (e.g., events arising from severe natural phenomena). If licensees are not in compliance, the information will allow NRC to assess how and when compliance with the applicable requirements will be achieved.


3. Reduction of Burden through Information Technology


There are no legal obstacles to reducing the burden associated with this information collection. The NRC encourages respondents to use information technology when it would be beneficial to them. The NRC issued a regulation on October 10, 2003 (68 FR 58791), consistent with the Government Paperwork Elimination Act, which allows its licensees, vendors, applicants, and members of the public the option to make submissions electronically via CD-ROM, e-mail, special Web-based interface, or other means. It is estimated the percentage of electronic submissions for these requirements will be similar to the percentage for other Part 50 requirements (approximately 54% of the responses are filed electronically.)


4. Effort to Identify Duplication and Use Similar Information


No sources of similar information are available.


5. Effort to Reduce Small Business Burden


The NRC has determined that the affected entities are not small entities or businesses as those terms are used in the Regulatory Flexibility Act.


6. Consequences to Federal Program or Policy Activities if the Collection Is Not Conducted or Is Conducted Less Frequently


If the information were not collected, or collected less frequently, the NRC would not have an efficient means of confirming whether licensees have improperly implemented and complied with the MBDBE rule, including developed training materials as well as documented training; or developed change control procedures, programs, or plans. Less frequent collection could adversely affect public health and safety.


7. Circumstances which Justify Variations from OMB Guidelines


This section identifies incremental recordkeeping and reporting burdens as a result of the rule that vary from OMB guidelines established in 5 CFR 1320.5(d)(2).


Operating reactors are required to comply with the information collections until the Commission terminates the license, which is initially issued for 40 years and may be subsequently renewed for an additional 20 years. Decommissioning reactors must comply with the information collection requirements until the spent fuel pools (SFPs) are empty of all irradiated fuel (or until an exemption is granted by the NRC). These requirements vary from the OMB guidelines in 5 CFR 1320.5(d)(2) (iv) by requiring licensees and other entities to retain records for more than 3 years. The specific provisions of the proposed rule that vary from OMB guidelines are Sections 50.155(a)(1) through (a)(2).


Per Section 50.155(a)(1), the requirements in Section 50.155 apply throughout the life of each site’s operating license, until the requirements are removed in accordance with the provisions in Section 50.155(a)(2) as discussed below.


Section 50.155(a)(2) establishes when these requirements end for licensees of decommissioning power reactors. This section allows licensees to end compliance with the portions of this rule that apply to the reactor source term and associated fission product barriers when all fuel has been permanently removed from the reactor vessel and placed in the SFP (i.e., no further requirement to comply with provisions that are associated with maintaining or restoring core cooling or primary containment functional capabilities). This section maintains SFP cooling for the SFP source term. This section allows licensees to end compliance with all the provisions in this rule once the SFP is empty of irradiated fuel.


These variations from the OMB guidelines are justified because the information collections are needed to ensure that the sites have the strategies and guidelines available to assist with the mitigation of beyond-design-basis events.


8. Consultations Outside the NRC


The information collection requirements were published for public comment in the Federal Register on November 13, 2015 (80 FR 70609). No comments were received on the proposed information collections as a result of public comment requests.


The MBDBE rulemaking consolidates two previous rulemaking efforts: the Station Blackout Mitigation Strategies (SBOMS) rulemaking and the Onsite Emergency Response Capabilities rulemaking. Both regulatory efforts offered extensive external stakeholder involvement opportunities, including public meetings, Advance Notices of Proposed Rulemaking (ANPRs) issued for public comment, and draft regulatory basis documents issued for public comment. The following were the major opportunities for stakeholder involvement:


    • Station Blackout ANPR (77 FR 16175, March 20, 2012)

    • Onsite Emergency Response Capabilities ANPR (77 FR 23161, April 18, 2012)

    • SBOMS draft regulatory basis and draft rule concepts (78 FR 21275, April 10, 2013)3

    • Onsite Emergency Response Capabilities draft regulatory basis (78 FR 1154, January 8, 2013)4

    • Preliminary proposed rule language for Onsite Emergency Response Capabilities (78 FR 68774, November 15, 2013)


The public has had additional opportunities to engage in these regulatory efforts for the MBDBE rulemaking. Most noteworthy were the following:


    • Consolidated rulemaking proof of concept language published on February 21, 2014 (ADAMS Accession No. ML14052A057)

    • Preliminary proposed rule language for consolidated rulemaking published August 15, 2014 (ADAMS Accession No. ML14218A253)

    • Preliminary proposed rule language for consolidated rulemaking published November 13, 2014 (ADAMS Accession No. ML14316A297), and December 8, 2014 (ADAMS Accession No. ML14336A641), to support public discussion with the Advisory Committee on Reactor Safeguards (ACRS)

    • Proposed MBDBE rulemaking issued for a 90-day public comment period on November 13, 2015 (80 FR 70609)

    • Public meeting held on January 21, 2016, to discuss the proposed rule with external stakeholders and thereby enable more informed feedback to be provided on the proposed rule

    • Public meeting held on November 10, 2016, to discuss the implementation schedule for the MBDBE rule and obtain feedback concerning cumulative effects of regulation, which could then be used to make appropriate adjustments to rule compliance dates


9. Payment or Gift to Respondents


Not applicable.

10. Confidentiality of Information


Confidential and proprietary information is protected in accordance with NRC regulations at 10 CFR 9.17(a) and 10 CFR 2.390(b).


11. Justification for Sensitive Questions


There are no sensitive questions included in these information collections.


12. Estimate of Industry Burden and Cost


During the clearance period, there are a total of 55 respondents to the information collection. All of these respondents are nuclear power reactor licensees. In the first three years after the effective date of the rule (the clearance period covered by this supporting statement):


Respondents will review the rule requirements and update site procedures, programs, or plans and maintain documentation of changes in the implementation of requirements.


The NRC staff estimates that applicants for power reactor operating licensees would require 300 hours to include plans for implementing the requirements in 10 CFR 50.155; however, no applications are anticipated during the clearance period.


The burden associated with the information collections is given in Tables 1-3. The one-time costs are annualized in this analysis by dividing by the number of years covered by the clearance (3 years). The annual fee rate of $265 is used for all costs. The total burden is 22,825 hours at a cost of $6,048,625 (22,825 x $265/hour). Annual recordkeeping burden begins the first year after the rule becomes effective with the licensees reviewing their previous compliance under Orders EA-12-049 and EA-12-051 against the MBDBE rule requirements to confirm their compliance with the MBDBE rule, as well as to make changes to procedures, programs, and plans to reference the new MBDBE rule requirements. The burden associated with this annualized recordkeeping is given in Table 2. The total annual burden is estimated as 22,825 hours at a cost of $6,048,625 (22,825 x $265/hour).


13. Estimate of Other Additional Cost


The NRC has determined that the records storage cost is roughly proportional to the recordkeeping burden cost. Based on a typical clearance, the recordkeeping storage cost has been estimated to be equal to 0.04 percent of the recordkeeping burden. Therefore, the additional recordkeeping storage cost for 10 CFR Part 50 is estimated to be $2,419 (22,825 recordkeeping hours x $265/hour x .0004), increasing the total additional costs for Part 50 from $269,617, to $272,036.


14. Estimated Annualized Cost to the Federal Government


The NRC staff does not anticipate any additional costs to the Federal Government based on the changes in this final rule. No power reactor operating licenses are anticipated and the remaining recordkeeping requirements do not require review by the NRC staff.


15. Reasons for Changes in Burden or Cost


The estimated burden for the information collections associated with the MBDBE final rule is 22,825 hours. This estimate is composed of one-time and ongoing annual reporting and recordkeeping requirements. This increases the burden for Part 50 information collections from 3,708,530 hours to 3,731,355 hours. There is no increase in the number of responses to the Part 50 information collection, as the 55 recordkeepers are already keeping other records under this collection.


The information collection requirements associated with the rule include reviewing the rule provisions to ensure that current practices satisfy the requirements of the rule; maintaining records of procedures, and program changes. The NRC anticipates that some changes may be needed to procedures, programs, or plans.


16. Publication for Statistical Use


The collected information is not published for statistical use.


17. Reason for Not Displaying the Expiration Date


The recordkeeping and reporting requirements for this information collection are associated with regulations and are not submitted on instruments such as forms or surveys.  For this reason, there are no data instruments on which to display an OMB expiration date.  Further, amending the regulatory text of the CFR to display information that, in an annual publication, could become obsolete would be unduly burdensome and too difficult to keep current.


18. Exceptions to the Certification Statement


None.


B. COLLECTION OF INFORMATION EMPLOYING STATISTICAL METHODS


Not applicable.




Table 1: Annualized One-Time Reporting Burden

Information Collection Section

Number of Respondents

Number of responses per respondent

Number of Responses

Burden Hours per Response

Total Annual Burden Hours

Cost @ $265/hr

10 CFR 50.34(i)







Part 50 applicants provide plans for implementing rule requirements in application

0

0

0

300

0

$0

Totals:

0

0

0

300

0

$0

Note: The burden hours per recordkeeper are based on the estimates used in the addenda to the regulatory analysis for the rule. The NRC burden hours in this supporting statement reflect the hours required for recordkeeping activities only, while the regulatory analysis includes hours for additional activities.


Table 2: One-Time Recordkeeping Burden

Information Collection Section

Number of Recordkeepers

Burden Hours per Recordkeeper

Total Annual Burden Hours

Cost @ $265/hr

10 CFR 50.155(a)(1)





Licensees review rule requirements and update procedures, programs, or plans

55

315

17,325

$4,591,125

Totals:

55

315

17,325

$4,591,125


Table 3: Annualized Recordkeeping Burden

Information Collection Section

Number of Recordkeepers

Burden Hours per Recordkeeper

Total Annual Burden Hours

Cost @ $265/hr

10 CFR 50.155(f)





Maintain documentation of changes in the implementation of requirements

55

100

5,500

$1,457,500

Totals:

55

100

5,500

$1,457,500




Total Burden Hours:

 

22,825

Total Burden Hour Cost:

 

$6,048,625 (22,825 x $265/hr)

Annual Respondents:

 

55

Responses:

 

55




1 Agencywide Documents Access and Management System (ADAMS) Accession No. ML12054A735

2 ADAMS Accession No. ML12056A044

3 The final regulatory basis was subsequently issued on July 23, 2013 (78 FR 44035).

4 The final Onsite Emergency Response Capabilities regulatory basis, with preliminary proposed rule language, was subsequently issued on October 25, 2013 (78 FR 63901).

8


File Typeapplication/vnd.openxmlformats-officedocument.wordprocessingml.document
File Modified0000-00-00
File Created2021-01-15

© 2025 OMB.report | Privacy Policy